Trench safety on a Calgary sewer dig: what Alberta's rules require

Alberta trench rules on a Calgary sewer replacement: the 1.5 m line, shoring or sloped walls by soil type, spoil piles, exits, water and foundations near the dig.

Conceptual illustration of ground conditions · protective system · safe exclusion
Illustrated field guideGround conditions · Protective system · Safe exclusionConceptual subject study · not a surveyed layout or field measurement
Short answer

Under Alberta's OHS Code, a worker may not enter an excavation deeper than 1.5 m, and closer to the wall than the excavation is deep, until the walls are cut back or supported by a temporary protective structure. Slopes depend on soil class, spoil must sit at least 1 m back from the edge, an exit must be within 8 m, and protective structures in excavations over 3 m deep must be engineered.

Key takeaways
  • The Code's protection rule applies to excavations more than 1.5 m deep when a worker is closer to the wall than the excavation's depth.
  • Soil class sets the slope: 30 degrees from vertical for hard and compact soil, 45 degrees for soil likely to crack or crumble, and from the bottom for soft, sandy or loose soil.
  • Ground that has been dug before, like an old sewer trench, cannot be treated as hard and compact under the Code's definitions.
  • Natural freezing of the soil is expressly not a substitute for a protective structure, a Calgary winter point worth knowing.
  • A foundation that may be affected by an excavation must be supported by an engineered temporary structure before the dig begins.
A shored trench across a front yard exposing an old clay sewer pipe
IllustrationOpen-cut repair: a shored trench exposing the old clay lateral.
Open-cut sewer trench in cross-sectionA trench cut across the line: spoil piled back from the edge, sloped or shored walls, a granular bedding layer under the new pipe, initial backfill around it, and native backfill compacted in lifts up to restored grade. SPOIL KEPT BACK ① BEDDING ② NEW PIPE ③ INITIAL BACKFILL ④ COMPACTED LIFTS DEPTH DEEP TRENCHES NEED SLOPING OR SHORING UNDER PROVINCIAL OHS RULES CROSS-SECTION · NOT TO SCALE
Fig. 1An open-cut trench: spoil kept back, protected walls, bedding under the pipe, backfill in compacted lifts.

01 /Why does trench safety change how a Calgary sewer job looks?

Trench protection decides the size of the hole, the equipment on site and how long the yard is open. A homeowner picturing a narrow slot from the house to the street is often surprised by a wide excavation with sloped sides, or by a steel trench box lowered in by the excavator. Both are the crew following Alberta's Occupational Health and Safety Code, Part 32, which governs excavating and tunnelling.

The reason is depth. In a house with a basement, the building drain leaves under the basement floor, so the lateral starts well below the yard surface and falls from there toward the street. For most of its length, a typical Calgary lateral runs deeper than the 1.5 m where the Code's protection requirements begin.

Open-cut sewer trench in cross-sectionA trench cut across the line: spoil piled back from the edge, sloped or shored walls, a granular bedding layer under the new pipe, initial backfill around it, and native backfill compacted in lifts up to restored grade. SPOIL KEPT BACK ① BEDDING ② NEW PIPE ③ INITIAL BACKFILL ④ COMPACTED LIFTS DEPTH DEEP TRENCHES NEED SLOPING OR SHORING UNDER PROVINCIAL OHS RULES CROSS-SECTION · NOT TO SCALE
Fig. 2The elements Alberta's rules shape: protected or sloped walls, spoil held back from the edge, a ladder or ramp within reach, bedding and pipe at the bottom.

02 /When must a sewer trench be shored or sloped?

The Code requires protection before a worker begins work in an excavation that is more than 1.5 m deep and where the worker is closer to the wall or bank than the depth of the excavation. The employer must protect the worker from cave-ins or sliding or rolling material by one of three approaches.

  1. Cutting back the walls so any remaining vertical wall is no more than 1.5 m high, for soil classed as hard and compact or likely to crack or crumble.
  2. Installing temporary protective structures, such as shoring, stringers and bracing, or a manufactured trench box.
  3. A combination of cutting back and protective structures.

Protective structures in excavations 3 m deep or less must be strong enough to stop the walls caving in or moving. In excavations more than 3 m deep they must be designed, constructed and installed to a professional engineer's specifications. The Code also allows lumber shoring built to its Schedule 9 in trenches from 1.5 m to 6 m deep. The only general exception is a trench in solid rock throughout, which a residential Calgary lateral does not meet.

03 /How does Calgary soil fit Alberta's soil classes?

Alberta's Code sorts soil into three classes, and the class sets how steeply walls may be cut. Calgary sites often contain more than one class in the same trench, and the Code says that when an excavation contains more than one soil type, the employer must treat all of it as the least stable type present.

Alberta OHS soil classes and the sloping rule for each (Part 32, sections 442 and 451)
Code classKey characteristics in the CodeWall slope if cut backWhere it turns up on a Calgary lot
Hard and compactHard, very dense, dry, no seepage, very hard to dig by hand, never excavated beforeSloped to within 1.5 m of the bottom at not less than 30 degrees from verticalUndisturbed stiff till away from the old sewer route
Likely to crack or crumblePreviously excavated, or stiff and compacted with surface cracking or local seepageSloped to within 1.5 m of the bottom at not less than 45 degrees from verticalThe backfill of the original sewer trench; weathered till
Soft, sandy or looseSoft or loose, flows when disturbed, runs into a cone when dry, wet, granular below the water tableSloped from the bottom at not less than 45 degrees from verticalSilt and fine sand layers, wet gravel, trenches below the water table

The replacement trench usually follows the old one, so the crew is digging through soil that was excavated when the house was built. Under the Code's definitions that ground cannot be classed as hard and compact. Add a gravel or silt lens and the whole trench may have to be treated as soft, sandy or loose. The Alberta Geological Survey's bulletin on the Calgary urban area describes lake sediments of silt and very fine sand and notes that quartzite gravel or hard sandstone under a thin cover of till or lake sediment makes digging difficult in many places. The soils and depth page maps those materials to parts of the city.

Generalized soil profile over a Calgary sewer lateralA generalized profile: topsoil over clay-rich glacial till with gravel and cobble lenses, a seasonal frost zone near the surface, and the sewer lateral typically a few metres down. Actual conditions vary from street to street. TOPSOIL SEASONAL FROST ZONE (DEPTH VARIES BY WINTER + COVER) SEWER LATERAL — OFTEN A FEW METRES DOWN (CONFIRM BY LOCATE) CLAY-RICH GLACIAL TILL GRAVEL / COBBLE LENS GROUND SURFACE GENERALIZED PROFILE · NOT A SITE INVESTIGATION
Fig. 3A generalized Calgary profile along a lateral: topsoil, clay-rich till, gravel and cobble lenses, and the frost zone. Mixed layers are treated as the least stable one present.

04 /What else do the rules require around the trench?

Other Part 32 rules that show up on a residential sewer dig
RuleWhat it requiresWhat you will see
Spoil pilesLeading edge at least 1 m from the excavation; slope no steeper than 45 degrees from horizontalDirt piled back from the edge, often on tarps or plywood
Safe entry and exitIn a trench more than 1.5 m deep, a safe way in and out within 8 m of the workerA ladder or ramp in the trench, moved as work advances
MarkingFlagging, marking or safeguards where a worker or equipment could fall inFencing, barricades or flagging around the open trench
WaterAn excavation a worker may enter is kept free of water that may pose a hazardA pump running, especially after rain or near river valleys
Loose materialLoose materials scaled and trimmed from the sides of the excavation and spoil pileCrew trimming the edges before entry
Power polesDigging must not reduce the support of nearby power polesExtra care or support near lane poles on back-lane routes

05 /What about digging next to the house foundation?

The Code says that before an excavation begins, a foundation that may be affected by it must be supported by a temporary protective structure designed, constructed and installed to a professional engineer's specifications. A sewer trench is deepest where it meets the house, because that is where the lateral leaves under the basement footing, so this is the spot to ask about.

  • Ask how the connection at the wall will be dug. Some crews make the exterior connection from a short, protected pit; others connect inside from the basement and start the trench further out.
  • Narrow inner-city lots can put a trench within a metre or two of a neighbour's foundation as well as your own. Ask whether the neighbour's wall is in the zone that needs support.
  • Existing cracks in your foundation or a neighbour's should be photographed before work starts.
  • Inside work under the basement slab involves cutting concrete and trenching indoors, with its own dust and access issues but a much shallower cut. See replacing the building drain under a basement floor.

If the contractor's answer is that the trench will be kept away from the foundation, ask how far and how the connection will be made. The answer affects the permit drawing, the price and where the machine sits.

06 /What should a homeowner watch for, and when should work stop?

You are not the site supervisor, but you are the one who sees the site every evening. These are reasonable things to notice and ask about, politely, the next morning or immediately if someone is in the trench.

  • A worker in a trench deeper than their waist with no box, shoring or sloped walls.
  • Spoil piled right at the edge, or a machine parked close to the edge.
  • Water pooling in the bottom, or walls weeping after rain or a thaw.
  • Cracks opening parallel to the trench on the surface nearby.
  • No ladder or ramp in a deep trench.
  • An open trench left overnight without fencing or covers where children or pets could reach it.

A crew that follows the rules will not mind the questions. For how a typical job unfolds hour by hour, see the day-by-day guide, and for the winter version, winter sewer replacement in Calgary. When comparing companies, the protection plan belongs in the quote; hiring a contractor includes it in the question list.

FAQQuestions people ask

At what depth does a trench need shoring in Alberta?

The OHS Code requires protection before a worker enters an excavation more than 1.5 m deep and is closer to the wall than the excavation's depth. Walls are cut back, supported by a protective structure, or both.

Does a sewer trench over 3 m need an engineer?

Temporary protective structures in excavations more than 3 m deep must be designed, built and installed to a professional engineer's specifications, though the Code also allows lumber shoring to its Schedule 9 in trenches up to 6 m.

How far from the trench must the dirt pile be?

The Code requires the leading edge of a spoil pile to be at least 1 m from the edge of the excavation, with the side facing the trench no steeper than 45 degrees.

Can frozen ground be used instead of shoring in winter?

No. The Code prohibits using natural freezing of the soil as an alternative or partial alternative to a temporary protective structure.

Why is my contractor's trench so wide?

Sloping the walls back is one of the Code's protection methods, and in soil that was dug before, the required angle takes a lot of width at a Calgary lateral's depth. A trench box keeps it narrower.

NETWORKGo deeper across the HAUSE Sewer network

Request quotes

Describe the problem once. Get a straight answer.

Send the symptoms and anything you already know — age of the house, what a camera found, what you have been quoted. The HAUSE Sewer desk replies with next steps and, where available, a local contractor for the job.

Sewage backing up right now? Stop using water, keep people away from the water, and do not touch electrical equipment near it.

Tell us about the job

Free request. We read every one and reply by email or phone.

HAUSE Sewer is an independent network, not a contractor. See our privacy notice.

The HAUSE Sewer network

One sewer line, every angle.